Does IKO Easyseal (2 layer system) have to be laid in 1 go or can I leave a day in between layers?

The underlay should be installed within 4 hours of the primer being cured to ensure good adhesion. The cap sheet could be installed at a later stage, just ensure that the underlay installed is free from water, dust, dirt etc by wiping clean prior to application.